File #: 22-539    Name:
Type: Staff Report Status: Consent Calendar
File created: 6/29/2022 In control: City Council
On agenda: 9/14/2022 Final action:
Title: Report regarding a motion to accept the construction improvements of the West Orange Avenue and Hillside Boulevard Pedestrian Crossing Enhancements Project (tr2001) as complete. (Jeffrey Chou, Associate Civil Engineer)
Attachments: 1. Attachment #1 - Project Locations Map, 2. Attachment 2 - Construction Photos
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Report regarding a motion to accept the construction improvements of the West Orange Avenue and Hillside Boulevard Pedestrian Crossing Enhancements Project (tr2001) as complete. (Jeffrey Chou, Associate Civil Engineer)

label
RECOMMENDATION
Recommendation
It is recommended that the City Council, by motion, accept the construction improvements of the West Orange Avenue and Hillside Boulevard Pedestrian Crossing Enhancements Project (tr2001) in accordance with plans and specifications (Total Construction Cost $172,024).

Body
BACKGROUND/DISCUSSION
On February 23, 2022, the City Council of South San Francisco awarded the West Orange Avenue and Hillside Boulevard Pedestrian Crossing Enhancements Project (tr2001) to Golden Bay Construction, Inc. to install pedestrian safety improvements including advanced pedestrian striping, high visibility crosswalks, and ADA curb ramps at the following locations:

* West Orange Avenue & Canal Street
* West Orange Avenue & Myrtle Avenue
* Hillside Boulevard & Claremont Drive

The Engineering Division inspected the work and found the project to be complete in accordance with the contract documents as of August 2, 2022. Project location map and construction photos are included as Attachments 1 and 2, respectively, of this staff report.

FISCAL IMPACT
The project is funded in the City of South San Francisco's fiscal year 2021-22 Capital Improvement Program (Project No. TR2001) with sufficient funds allocated to cover the Total Construction Budget.
The total construction cost incurred for the project is summarized as follows:
Projected Actual
Construction Contract $167,756 $167,756
Construction Contingency (actual ~2%) $ 33,551 $ 4,268
Total Project Construction Budget $201,307 $172,024

The program includes $204,000 of Highway Safety Improvement Program (HSIP) Federal funds with the remaining funding coming from the Measure A Gas Tax funding source. If there's remaining local funds ava...