File #: 24-107    Name:
Type: Resolution Status: Passed
File created: 1/29/2024 In control: City Council
On agenda: 2/28/2024 Final action: 2/28/2024
Title: Resolution awarding a construction contract to Wickman Development and Construction of Oakland, California for the Capital Improvement Project No. pk2310 (Bid No. 2687) in an amount not to exceed $34,790,000 and authorizing a total project budget of $38,269,000.
Sponsors: City Council
Attachments: 1. Exhibit A - Owner-Contractor Agreement
Related files: 24-106
Title
Resolution awarding a construction contract to Wickman Development and Construction of Oakland, California for the Capital Improvement Project No. pk2310 (Bid No. 2687) in an amount not to exceed $34,790,000 and authorizing a total project budget of $38,269,000.

body
WHEREAS, the Orange Memorial Park Aquatic Center Project ("Project") completed a prequalification process for general contractors and a competitive bid process; a total of seven general contractors were prequalified and of those seven, four submitted a bid; Wickman Development and Construction is the lowest responsible bidder; and

WHEREAS, Wickman Development and Construction will be subject to Prevailing Wage rates in constructing the Project; and

WHEREAS, total construction duration is 18 months; 563 calendar day construction period from date of Notice to Proceed, which includes a clause for liquidated damages in the amount of $4,000.00 for each calendar day delay in completion; and

WHEREAS, Wickman Development and Construction will comply with insurance requirements as outlined in Article 11 of the General Conditions and provide corresponding Labor and Material Payment Bond and a Contractor's Performance Bond in the amount of 100% of contract price; and

WHEREAS, City staff recommends award of the construction contract to Wickman Development as the lowest bidder and the execution of the contract for the construction of the Project; and

WHEREAS, funding for this Project is included in the City of South San Francisco's Orange Memorial Park Aquatic Center budget, project pk2310.

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of South San Francisco that the City Council hereby awards a construction contract, a draft of which is attached hereto as Exhibit A and incorporated herein, for the Orange Memorial Park Aquatic Center Project to Wickman Development and Construction of Oakland, California, in an amount not to exceed $34,790,000 conditioned on a construction pe...