File #: 18-682    Name:
Type: Resolution Status: Passed
File created: 7/19/2018 In control: City Council
On agenda: 8/28/2019 Final action: 8/28/2019
Title: Resolution rejecting all bids for the Linden Ave. Complete Streets (Aspen to Miller) Phase II/ Spruce Ave (Lux Ave to Maple Ave) Project. (Matthew Ruble, Principal Engineer)
Related files: 18-681

Title

Resolution rejecting all bids for the Linden Ave. Complete Streets (Aspen to Miller) Phase II/ Spruce Ave (Lux Ave to Maple Ave) Project. (Matthew Ruble, Principal Engineer)

 

 

 

body

WHEREAS, on June 25, 2019, the City of South San Francisco (“City”) staff issued a Notice Inviting Bids for the Linden Ave. Complete Streets (Aspen to Miller) Phase II/ Spruce Ave (Lux Ave to Maple Ave) Project, Project No. st1602 and on August 8, 2019 received three (3) bids in response; and

 

WHEREAS, the three bids received were substantially higher than the engineer’s estimate and the project construction budget; and

 

WHEREAS, pursuant to Public Contract Code Section 20166, a legislative body of a public entity may reject any bids received for a public project; and

WHEREAS, the City has determined that it will need to review and revise the contract scope of work and then rebid the project.

NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of South San Francisco that the City Council hereby rejects all bids for the Linden Ave. Complete Streets (Aspen to Miller) Phase II/ Spruce Ave (Lux Ave to Maple Ave) Project and authorizes City staff to readvertise the Project.

 

 

*                                          *                                          *                                          *                                          *