Title: Report regarding a motion to accept the construction improvements of the South San Francisco Bicycle and Vehicle Pavement Delineation Project (Project No. tr1503) as complete in accordance with plans and specifications (Total Construction Cost $224,443.87). (Jason Hallare, Associate Civil Engineer)
Title
Report regarding a motion to accept the construction improvements of the South San Francisco Bicycle and Vehicle Pavement Delineation Project (Project No. tr1503) as complete in accordance with plans and specifications (Total Construction Cost $224,443.87). (Jason Hallare, Associate Civil Engineer)

label
RECOMMENDATION
It is recommended that the City Council, by motion, accept the construction improvements of the South San Francisco Bicycle Vehicle Pavement Delineation Project (Project No. tr1503) as complete in accordance with plans and specifications (Total Construction Cost $224,443.87).

Body
BACKGROUND/DISCUSSION
On November 28, 2018, the City Council of South San Francisco awarded the South San Francisco Bicycle Vehicle Pavement Delineation Project (Project No. tr1503) to Chrisp Company to refresh existing striping and markings and/or install new striping and markings along Westborough Boulevard, from Skyline Boulevard to Interstate 280 Southbound Off-ramp and along Junipero Serra Boulevard, from Westborough Boulevard to Hickey Boulevard.

In addition to the above limits, staff took the opportunity to have the contractor refresh existing striping along Hickey Boulevard, from Hilton Avenue to El Camino Real, and along Westborough Boulevard from Camaritas Avenue to El Camino Real. Additionally, staff had the contractor refresh a crosswalk on C-Street in response to a walk audit for Los Cerritos Elementary.

The total construction cost incurred for the project is summarized as follows:
Projected Actual
Chrisp Company Construction Contract $ 190,744.00 $ 190,744.00
Construction Contingency (15 percent) $ 28,611.00 $ 22,857.40
Construction Management / Administration (10 percent) $ 19,074.40 $ 10,842.47
Total Project Budget $ 238,429.40 $ 224,443.87

FUNDING
Funding for this project was included in the City of South S...

Click here for full text