Title: Resolution authorizing the continuation of emergency repair work to address the storm drain failure and related repairs on Junipero Serra Boulevard near Westborough Boulevard.
Related files: 18-277
Title
Resolution authorizing the continuation of emergency repair work to address the storm drain failure and related repairs on Junipero Serra Boulevard near Westborough Boulevard.

body
WHEREAS, on February 14, 2018, City Council adopted a resolution authorizing emergency repair work to address the storm drain failure located in the vicinity of Junipero Serra Boulevard, just north of Westborough Boulevard; City Council authorized an agreement with Interstate Grading & Paving of South San Francisco, CA ("Contractor") to perform the repair work in the amount of $537,525; and City Council approved Budget Amendment No. 18.023 in the amount of $663,525 to cover the cost of the emergency repair project; and

WHEREAS, City Council also authorized an agreement with Cotton Shires & Associates to design and inspect the repair work, and to be present on-site during the emergency repair work to provide additional engineering assessments as necessary due to the urgent and unforeseen nature of the proposed repair work; and

WHEREAS, the authorized repair work is to clear out the debris, stabilize the undermined cavity with engineered fill and fix the storm drain lines, and reconstruct the failed portion of the roadway accordingly; and

WHEREAS, on March 14, 2018, City Council approved Budget Amendment No. 18.026 in the amount of $23,845, increasing the total emergency repair project budget to $687,371; and

WHERAS, on March 28, 2018, City Council adopted a resolution authorizing further continuation of emergency repair work to address the storm drain failure and related repairs on Junipero Serra Boulevard near Westborough Boulevard; and

WHEREAS, to date, the Contractor has continued the traffic control on Junipero Serra by installing K-rails, cleared and grubbed the affected area, removed the unsafe street section, plugged the storm drain system to prevent any storm water from further erosion, and stabilized the area; and

WHEREAS, the repair work has made slow progress ...