City of South San Francisco header
File #: 23-260    Name:
Type: Motion Status: Passed
File created: 3/29/2023 In control: City Council
On agenda: 5/10/2023 Final action: 5/10/2023
Title: Motion to accept the construction improvements of the Water Quality Control Plant (WQCP) Secondary Clarifiers No. 1 and No. 2 Rehabilitation Project (Project No. ss1703) as complete in accordance with plans and specifications (Total Construction Cost $4,154,104.56) (Brian Schumacker, Water Quality Control Plant Superintendent/Project Manager)
Attachments: 1. Visual Report WQCP Secondary Clarifier Rehabilitation Project
Title
Motion to accept the construction improvements of the Water Quality Control Plant (WQCP) Secondary Clarifiers No. 1 and No. 2 Rehabilitation Project (Project No. ss1703) as complete in accordance with plans and specifications (Total Construction Cost $4,154,104.56) (Brian Schumacker, Water Quality Control Plant Superintendent/Project Manager)

label
RECOMMENDATION
Staff recommends that the City Council, by motion, accept the construction improvements of the WQCP Secondary Clarifiers No. 1 and No. 2 Rehabilitation Project (Project No. ss1703) as complete in accordance with plans and specifications (Total Construction Cost $4,154,104.56)

Body
BACKGROUND/DISCUSSION
On October 14, 2020, the City Council of South San Francisco awarded the WQCP Secondary Clarifiers No. 1 and No. 2 Rehabilitation Project (Project No. ss1703) to Western Water Construction Inc. The project scope included replacing the clarifier mechanisms, RAS/WAS pumps, major process piping and valves with new equipment. Further, contractors also performed concrete and coating rehabilitation of the two clarifiers and the pump station.
Projected Actual
Western Water Construction Inc. Contract $ 3,526,000.00 $ 3,526,000.00
Construction Contingency (20%) $ 705,200.00 $ 306,904.56
Construction management (10%) $ 352,600.00 $ 321,200.00
Total Project Construction Budget $ 4,583,800.00 $ 4,154,104.56

FUNDING
This project is funded by Sewer Enterprise Funds and is included in the City of South San Francisco's Fiscal Year 2020-2021 Capital Improvement Program (Project No. ss1703) with sufficient funds allocated to cover the project cost.

RELATIONSHIP TO STRATEGIC PLAN
Project acceptance will contribute to the City's Strategic Plan outcome of improved Quality of Life by continuing the operation of the South San Francisco / San Bruno Water Quality Control Plant and promotes public health and environmental stewardship. Proper infrastructure maintenance positively af...

Click here for full text