Title
Motion to accept the construction improvements of the Oyster Point Boulevard Sanitary Sewer Main Reconstruction Project (No. ss2401, Bid No. 2690) as complete in accordance with plans and specifications at a total construction cost of $4,370,869.80. (Jeffrey Chou, Senior Civil Engineer)
label
RECOMMENDATION
Recommendation
It is recommended that the City Council, by motion, accept the construction improvements of the Oyster Point Boulevard Sanitary Sewer Main Reconstruction Project (No. ss2401, Bid No. 2690) as complete in accordance with plans and specifications at a total construction cost of $4,370,869.80.
Body
BACKGROUND/DISCUSSION
On May 28, 2025, the City awarded a construction contract to K.J. Woods Construction, Inc. to upsize the existing sanitary sewer main along Oyster Point Boulevard, from Gull Drive to the sanitary sewer pump station at Gateway Boulevard, by installing a new 18-inch high-density polyethylene (HDPE) standard dimension ratio (SDR) -17 pipeline to replace the existing 10-inch sewer main.
The project was identified through the City's Sanitary Sewer Master Plan as a critical capacity improvement needed to accommodate peak wet-weather flows and support the long-term reliability of the wastewater collection system. The existing 10-inch sewer main represented a hydraulic bottleneck within the system and had the potential to contribute to surcharging and sanitary sewer overflows during significant storm events.
Completion of the project has increased conveyance capacity within this section of the sanitary sewer system, reducing the risk of sanitary sewer overflows and improving system reliability during peak wet-weather conditions. The project also supports the City's ongoing efforts to maintain regulatory compliance and protect public health and the environment.
In addition, the project included asphalt road grind-and-overlay and restriping of the eastbound travel lanes on Oyster Point Boulevard and a portion of Veterans Boule...
Click here for full text