Legislation Details

File #: 26-2075    Name:
Type: Resolution Status: Consent Calendar
File created: 7/15/2026 In control: City Council
On agenda: 8/26/2026 Final action:
Title: Resolution approving a Third Amendment to an existing consulting services agreement with Swinerton Management and Consulting for construction management services of the Orange Memorial Park Aquatic Center project in an amount not to exceed $483,945, increasing the total contract authorization to $2,879,335 and authorizing the City Manager or designee to execute the amendment.
Sponsors: City Council
Attachments: 1. Exhibit A - Swinerton Third Amendment for OMPAC, 2. Exhibit B - Swinerton Second Amendment for OMPAC - signed, 3. Exhibit C - Swinerton Proposal
Related files: 26-2072
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Resolution approving a Third Amendment to an existing consulting services agreement with Swinerton Management and Consulting for construction management services of the Orange Memorial Park Aquatic Center project in an amount not to exceed $483,945, increasing the total contract authorization to $2,879,335 and authorizing the City Manager or designee to execute the amendment.

body
WHEREAS, on May 11, 2022, the City Council approved a Consulting Services Agreement with Swinerton Management and Consulting of San Francisco, California ("Consultant") to provide construction management services for the Orange Memorial Park Aquatic Center Project (pk2310) in an amount not to exceed $1,946,060; and

WHEREAS, in February 2024, a construction contract was awarded to Wickman Development and Construction for the Orange Memorial Park Aquatic Center (pk2310), and

WHEREAS, a First Amendment to the Consulting Services Agreement was executed between City and Consultant on December 31, 2024, extending the date for the term of services to December 31, 2026, and

WHEREAS, the City Council approved a Second Amendment to the Consulting Services Agreement on February 25, 2025, increasing the total contract amount by $251,424 and

WHEREAS, Consultant has performed satisfactorily throughout the design and construction of the Orange Memorial Park Aquatic Center Project and has provided the services required under the Agreement; and

WHEREAS, the construction schedule for the Orange Memorial Park Aquatic Center Project has been extended, with substantial completion and project closeout now anticipated in early 2027, requiring continued construction management services during construction and closeout; and

WHEREAS, staff recommends approval of a Third Amendment to the Consulting Services Agreement with Consultant in an amount not to exceed $483,945 to provide continued construction management services through project completion; and

WHEREAS, as part of the adopted Fiscal Year ...