File #: 25-1098    Name:
Type: Staff Report Status: Passed
File created: 10/14/2025 In control: City Council
On agenda: 12/10/2025 Final action: 12/10/2025
Title: Motion to accept the construction improvements of the Oyster Point Phase IIC Improvement Project (Project Nos. pf2204/pf2205/pf2206) as complete in accordance with plans and specifications (total construction cost $4,570,144.55). (Philip Vitale, Deputy Director of Capital Projects)
Sponsors: City Council
Attachments: 1. Attachement 1 - Notice of Completion
Title
Motion to accept the construction improvements of the Oyster Point Phase IIC Improvement Project (Project Nos. pf2204/pf2205/pf2206) as complete in accordance with plans and specifications (total construction cost $4,570,144.55). (Philip Vitale, Deputy Director of Capital Projects)

label
RECOMMENDATION
It is recommended that the City Council, by motion, accept the construction improvements of the Oyster Point Phase IIC Improvement Project (Project Nos. pf2204/pf2205/pf2206) as complete in accordance with plans and specifications (total construction cost $4,570,144.55).

Body
BACKGROUND/DISCUSSION
The area known as Oyster Point is in the northeastern portion of South San Francisco, accessed by Oyster Point Boulevard. Built above a capped landfill, the area has seen significant improvements over the past several years. Much of the area has been improved in partnership between the City of South San Francisco and private developers. The area known as IIC is on the eastern half of the Oyster Point peninsula and owned by the City of South San Francisco and operated by the San Mateo County Harbor District. Portions of the area fall within the San Francisco Bay Conservation and Development Commission (BCDC) jurisdiction. Through a development permit originally issued by BCDC in 1979, along with subsequent amendments, the Harbor District developed a Marina along with other elements, including the Bay Trail. Through an agreement with the former Redevelopment Agency, funds were made available to the City of South San Francisco to perform maintenance and repairs to the landscape, parking area, and Bay Trail within area IIC while maintaining the site program.

On October 11, 2023, City Council awarded the Oyster Point Phase IIC Improvement Project (CIP Project Nos. pf2204/pf2205/pf2206) to GECMS Inc. dba Giron Construction of San Francisco, California. The improvements associated with this project were completed in October 2025.
The improvements included repairs t...