Capital Projects Update. (Philip Vitale, Deputy Director of Capital Projects)
label
RECOMMENDATION
Recommendation
It is recommended that the Parks and Recreation Commission receive an update on the Linden Avenue Park Project, Orange Memorial Park Aquatic Center Project, Orange Memorial Park Main Playground Replacement Project and Centennial Trail Park North Project.
Body
BACKGROUND/DISCUSSION
Linden Park Project Update pk2305)
Following City Council's award of the construction contract to Azul Works, Inc. in April 2026, the City celebrated the groundbreaking of the Linden Park Project on May 8, 2026. The event was well attended by community members, project stakeholders, and funding partners, including Congressman Kevin Mullin and California State Parks District Superintendent Chris Spohrer.
Construction activities began in June 2026. Prior to mobilization, nearby residents and businesses received construction notices describing Phase 1 work, anticipated traffic impacts, and contact information for the contractor and construction management team. Construction signage containing project information and contact details was also installed at the site.
Phase 1 construction focuses on installation of the Pine Avenue Bypass Road, allowing Pine Avenue to remain open during the initial stages of construction.
Construction notices were distributed in early July 2026. Phase 2A included installation of construction fencing around the 700 Linden parcel and the remaining portions of the 616 Linden parcel. Pine Avenue and adjacent sidewalks remain open during this phase while demolition of the existing parking lot, site clearing, and tree removal are underway.
Upon completion of the Pine Avenue Bypass Road, traffic will be shifted onto the new roadway and Phase 2 construction will begin. This phase will require closure of Pine Avenue within the project limits while maintaining pedestrian access along the Linden Avenue sidewalk adjacent to the project site. A te...