City of South San Francisco header
File #: 24-1127    Name:
Type: Presentation Status: Agenda Ready - Presentations
File created: 11/12/2024 In control: Parks and Recreation Commission
On agenda: 11/19/2024 Final action:
Title: Capital Projects Update (Philip Vitale, Deputy Director of Capital Projects)
Attachments: 1. Presentation, 2. Oyster Point 2C Flyer, 3. Veteran’s Memorial Survey flyer, 4. Linden Park Design Alts Eng. Summary
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Capital Projects Update (Philip Vitale, Deputy Director of Capital Projects)

label
RECOMMENDATION
Recommendation
It is recommended that the Parks and Recreation Commission receive an update on the Oyster Point IIC, Orange Memorial Park Aquatics Center, Orange Memorial Park Veteran's Memorial and the New Park at Linden and Pine projects.

Body
BACKGROUND/DISCUSSION

Oyster Point IIC
The notice to proceed for construction was issued to GECMS, Inc. in January 2024. Construction is advancing as the contractor continues installation of site furnishings, signage, plantings and drainage areas. The dog area has been mulched and the walking pathway installed. Trees, shrubs, groundcover and irrigation installation is nearly complete and the resurfaced parking lot is open. The north-south connector spur of the Bay Trail is anticipated to open the week of November 18. Construction of Phase 1 is scheduled to be complete by late November with a Ribbon Cutting ceremony planned to coincide with the annual South San Francisco Fun Run event on Saturday, November 23. Construction of Phase 2, which includes plantings at the westernmost portion of the project will start late November.

Orange Memorial Park Aquatics Center
The notice to proceed for construction was issued to Wickman Development and Construction in April 2024. Excavation was completed early November. Installation of grade beams and other foundation pieces will be formed and poured over the coming weeks. Steel structures are scheduled to begin arriving on site in December. Material delivery will occur through the vehicular gate on Orange Ave. The Tennis Drive parking lot remains open for Orange Pool users. A live camera feed of construction activities is available on the project webpage.

Orange Memorial Park Veteran's Memorial
A new Veteran's Memorial will be constructed as part of the new Orange Memorial Park Aquatics Center project. The memorial will honor and respect the service of Veterans, with a fres...

Click here for full text