Title: Resolution authorizing a First Amendment to the Services Agreement with Wastewater Solids Management Company for anaerobic digester cleaning services in an amount not to exceed $97,500, increasing total contract authority to $727,863 and extending the agreement term, and authorizing the City Manager or designee to execute the agreement on behalf of the City.
Attachments: 1. Exhibit A - Draft Wastewater Solids First Amendment
Related files: 26-2115
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Resolution authorizing a First Amendment to the Services Agreement with Wastewater Solids Management Company for anaerobic digester cleaning services in an amount not to exceed $97,500, increasing total contract authority to $727,863 and extending the agreement term, and authorizing the City Manager or designee to execute the agreement on behalf of the City.

Body
WHEREAS, the City of South San Francisco (“City”) maintains critical infrastructure assets associated with the wastewater treatment plant such as their digesters and storage tanks; and

WHEREAS, routine proper maintenance of these assets, including cleaning, solids removal, screening, and on-site dewatering of sludges, is essential to preserving reliability, extending equipment service life, and ensuring the long-term dependability of the City’s vital infrastructure systems; and

WHEREAS, a specialized company is required to provide digester dewatering and cleaning services; and

WHEREAS, the City Council previously approved a services agreement with Wastewater Solids Management Company for routine solids removal and dewatering of five (5) Water Quality Control Plan (WQCP) vessels, authorized contract authority of $630,363; and

WHEREAS, following initial cleaning operations, staff inspected the interior of Digester No. 1 and identified an unanticipated industrial coating failure on the interior roof coating; and

WHEREAS, Digester No. 5 contained more material buildup than estimated during bidding; and

WHEREAS, a separate city-contracted industrial coating company performed critical interior roof industrial recoating, generating structural grit blasting, overspray, and debris that impacted the newly cleaned vessel interior; and

WHEREAS, to preserve infrastructure integrity and protect downstream process equipment from damage by abrasive debris, the affected digester requires a general recleaning, secondary solids evacuation, and final high-pressure washdown; and

WHEREAS, Wastewater Solids M...