City of South San Francisco header
File #: 19-1029    Name:
Type: Staff Report Status: Public Hearing
File created: 12/23/2019 In control: Planning Commission
On agenda: 3/5/2020 Final action:
Title: Report regarding consideration of a Precise Plan and Design Review to construct Phases 2D, 3D and 4D of the Oyster Point Redevelopment Project, including 1,707,000 sq. ft. of Office/R&D development, 48,000 sq. ft. of amenity space, two parking garage structures to accommodate 4,445 parking spaces, improvement of waterfront trail and open spaces within the development, and other on- and off-site improvements, at 377-389 Oyster Point Boulevard, and determination that the project is within the scope of environmental analysis in the 2011 Environmental Impact Report (EIR) and no further environmental analysis would be required pursuant to CEQA Guidelines. (Billy Gross, Senior Planner)
Attachments: 1. Att 1 - 2011 OP Specific Plan, 2. Att 2 - Oyster Point Precise Plan 1D Project Plans, 3. Att 3 - 2011 Oyster Point DDA, 4. Att 4 - Design Review Board 11-19-19 Minutes
Related files: 20-127, 19-1030
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Report regarding consideration of a Precise Plan and Design Review to construct Phases 2D, 3D and 4D of the Oyster Point Redevelopment Project, including 1,707,000 sq. ft. of Office/R&D development, 48,000 sq. ft. of amenity space, two parking garage structures to accommodate 4,445 parking spaces, improvement of waterfront trail and open spaces within the development, and other on- and off-site improvements, at 377-389 Oyster Point Boulevard, and determination that the project is within the scope of environmental analysis in the 2011 Environmental Impact Report (EIR) and no further environmental analysis would be required pursuant to CEQA Guidelines. (Billy Gross, Senior Planner)

label
RECOMMENDATION
Recommendation
Staff recommends that the Planning Commission conduct a public hearing and take the following actions:
1. Adopt a Resolution making findings and determining that the Oyster Point Phase 2D, 3D and 4D Precise Plans Project is fully within the scope of environmental analysis in the 2011 Environmental Impact Report, and that the 2020 Environmental Checklist to the 2011 EIR is the appropriate environmental document for the Project and thus no subsequent environmental document would be necessary pursuant to the criteria of CEQA Guidelines Section 15162; and,

2. Adopt a Resolution making findings and approving Precise Plan PP19-0001 and Design Review DR19-0034, based on the attached draft findings and subject to the attached draft conditions of approval.

Body
BACKGROUND/DISCUSSION

2011 Oyster Point Redevelopment Project Overview
In 2011, the City Council approved a General Plan Amendment, Zoning Ordinance Amendment, Downtown/Central Redevelopment Plan Amendment, Disposition and Development Agreement, Development Agreement, Transportation Demand Management Program and Precise Plan for the Oyster Point Redevelopment Project. The overall Project approvals include approximately 2.25 million square feet (sq. ft.) of office/research and development ...