Report regarding an update on the Linden Avenue Park Project (project no. pk2305) and Orange Memorial Park Aquatic Center Project (project no. pk2310). (Philip Vitale, Deputy Director of Capital Projects)
label
RECOMMENDATION
Recommendation
It is recommended that the Parks and Recreation Commission receive an update on the Linden Avenue Park Project and Orange Memorial Park Aquatic Center Project.
Body
BACKGROUND/DISCUSSION
Linden Avenue Park Project Update
Following an extensive community engagement process and recommendations from the Public Art Subcommittee and Cultural Arts Commission, the City Council awarded a contract to J. Muzacz for the design and installation of public art at the new Linden Avenue Park. The artwork will incorporate community participation through a mosaic installation event anticipated in late 2026, providing residents with an opportunity to directly contribute to the final pieces.
A Request for Bids for park construction was publicly advertised on February 11, 2026. Bid documents are available under pk:2305: New Park at Linden and Pine Ave Construction at OpenGov.com. Questions regarding the bid documents are due February 25, and bids are scheduled to be received on March 11.
On September 30, 2025, the City launched the Throne Restroom Pilot at 700 Linden Avenue near 8th Lane to assess restroom access solutions in advance of permanent park construction. The restroom is accessible via QR code, text message, or free access cards available at the Grand Avenue Library. Signage is provided in English and Spanish.
The following summarizes pilot performance data through December 2025:
* Total Usage: 1,844 visits recorded
* Repeat Usage: Over 35% of users are returning visitors
* Peak Demand: Highest utilization occurs on weekends
* Accountability: No users required access restrictions due to misuse
* Cleanliness Rating: Average user satisfaction score of 4.22 out of 5.00
To evaluate impacts on the surroun...