Title
Motion to accept the construction improvements of Community Civic Campus: Phase II Library, Parks & Recreation and Community Theater/Council Chamber (No. pf1707) as complete in accordance with plans and specifications (total construction cost $95,696,167). (Jacob Gilchrist, Director of Capital Projects)
label
RECOMMENDATION
Recommendation
It is recommended that the City Council, by motion, accept the construction improvements of Community Civic Campus: Phase II Library, Parks & Recreation and Community Theater/Council Chamber (No. pf1707) as complete in accordance with plans and specifications (total construction cost $95,696,167).
Body
BACKGROUND/DISCUSSION
Library | Parks and Recreation was originally envisioned as part of the Community Civic Campus in 2015 and, following the passage of Measure W, was developed as Phase II of the Community Civic Campus, following the Police Operations and 9-1-1 Dispatch Center, and preceding Fire Station 63. As the primary project of the 2021A Lease Revenue Bond Series, the project's construction contract was awarded by the City Council on November 9, 2020, with an additional $1 million of bond funds set aside to install a solar panel array on the building. At that time, staff anticipated adding several elements to the project as additional funding became available via fundraising and grant-writing. More than $8 million in additional funding was raised for the project.
The use of $4.3 million of additional construction contract contingency noted below reflects additional project enhancements including:
* electrical infrastructure costs to shift building to be an all-electric facility
* rooftop solar panel array
* exterior digital sign at Chestnut Avenue and El Camino Real
* exterior security cameras
* AV/IT infrastructure to support remote meetings in meetings and Library collaboration rooms
* anti-graffiti coating on exterior concrete
The total construction contract cost incurred for the project is summarized as ...
Click here for full text