Title
Motion to accept the construction improvements of the HSIP Curb Ramp Improvements Project (tr2202) as complete in accordance with plans and specifications (Total Construction Cost $696,574.53). (Audriana Hossfeld, Senior Civil Engineer)
label
RECOMMENDATION
It is recommended that the City Council, by motion, accept the construction improvements of the Local Highway Safety Improvement Program Curb Ramp Improvements Project (tr2202) as complete in accordance with plans and specifications (total construction cost $696,574.53).
Body
BACKGROUND/DISCUSSION
On December 13, 2023, City Council awarded the Local Highway Safety Improvement Program (HSIP) Curb Ramp Improvements Project (tr2202) to RK Engineering of San Francisco, California.
The HSIP - Curb Ramp Replacement Project installed ADA-compliant curb ramps at five (5) unsignalized intersections:
* Walnut Avenue and Lux Avenue
* Walnut Avenue and Park Way
* Olive Avenue and Pine Avenue
* Olive Avenue and Aspen Avenue
* Linden Avenue and 8th Lane
The work completed consisted of replacing existing concrete curb ramps or corners with ADA- compliant curb ramps, replacing sections of existing fractured or settled curb and gutter, replacing sections of existing fractured sidewalk where necessary, and reinstalling traffic striping at five (5) locations.
The Engineering Division inspected the work and found the project to be complete in accordance with the contract documents as of June 24, 2024. This staff report includes the project location map and construction photos as Attachments 1 and 2, respectively.
FISCAL IMPACT
This project (tr2202) is included in the City of South San Francisco's fiscal year (FY) 2023-24 budget. There are sufficient funds in FY 2023-24 to cover the total construction contract costs.
The total construction cost incurred for the project is summarized as follows:
Projected
Actual
RK Engineering
$676,580.00
$673,943.35
Construction Contingency
$135,316.00
$22,631.18
Total Construction...