Title
Motion accepting the South San Francisco/San Bruno Water Quality Control Plant (WQCP) Wet Weather and Digester Improvements Project (Project No. ss1301) as complete per plans and specifications (Total Construction Cost $53,730,227.00). (Brian Schumacker, Water Quality Control Plant Superintendent)
label
RECOMMENDATION
Staff recommends that the City Council, by motion, accept the construction improvements of the WQCP Wet Weather and Digester Improvement Projects (Project No. ss1301) as complete per plans and specifications (Total Construction Cost $53,730,227.00)
Body
BACKGROUND/DISCUSSION
On July 11, 2018, the City Council of South San Francisco awarded the WQCP Wet Weather and Digester Improvements Project (Project) to Flatiron West, Inc. Carollo Engineers, designed the Project to comply with the City’s National Pollution Discharge Elimination System (NPDES) permit requirements.
The Project includes two project elements:
1. Mandated Wet Weather Flow Improvements: This project element increases the peak secondary treatment capacity at the WQCP by ten million gallons per day (MGD) to a total capacity of 40 MGD by:
a. Installing a new secondary clarifier with associated equipment and piping, and
b. Upgrading associated secondary treatment facilities such as improvements to the aeration basins. These improvements will enhance sludge settleability, increase flow conveyance to the secondary treatment system and increase automation of the treatment process.
This element also includes construction of two storm water pump stations and associated piping systems to capture and treat stormwater runoff from the plant grounds.
2. Mandated Digester Replacement and Rehabilitation: This project element replaces/rehabilitates aging infrastructure and improves WQCP reliability. The element includes demolition of two of the five existing digesters (Digester No’s. 1 and 2). The element replaces these two digesters with one new digester (utilizing a high-solids digestion system) and rehabilitating a digester (Digester No. 3) to withstand stronger seismic events. One associated support building, which houses heating and mixing equipment, was demolished as part of this element. This element also includes the addition of digested sludge thickening equipment, a polymer storage facility, and a digester gas conditioning system. These systems will improve the reliability, service life and overall efficiency of the existing cogeneration engine to produce electrical power for the WQCP.
The total construction cost incurred for the project is summarized as follows:
Projected Actual
Flatiron West, Inc. Contract $49,601,891.00 $49,579,559.50
Construction Contingency $ 4,180,045.00 $ 4,150,667.50
Total Project Construction Budget $53,781,936.00 $53,730,227.00
The projected construction contingency above includes $1.7 million which the City Council approved by Resolution on May 25, 2022.
FISCAL IMPACT
This project is funded by the Sewer Enterprise Fund, the City of San Bruno, and the State of California State Revolving Fund (SRF). As a co-owner of the WQCP, San Bruno’s share is 26.92% of the project costs or approximately $16.6 million. The project is included in the City of South San Francisco’s fiscal year 2017-18 Capital Improvement Program (Project No. ss1301). The SRF Fund is providing loan funding of $53,403,000 for Project construction and construction management and administration, with $4,000,000 of loan forgiveness from the SRF Green Project Reserve fund.
RELATIONSHIP TO STRATEGIC PLAN
Approval of this action will contribute to the City’s Strategic Plan outcome of improved quality of life by continuing the operation of the South San Francisco - San Bruno Water Quality Control Plant.
CONCLUSION
Staff recommends acceptance of the project as complete. Upon City Council’s motion to accept the project, The City of South San Francisco will file a notice of completion with the County of San Mateo Recorder’s office. At the end of the thirty-day lien period, South San Francisco will release retention funds to the contractor after the City receives a one-year warranty bond.
Staff recommends that the City Council, by motion, accept the WQCP Wet Weather and Digester Improvements Project (Project No. ss1301) as complete per plans and specifications (Total Construction Cost $53,730,227.00).