Title: Informational Report on Measure W FY 2023-24 financials update for Measure W. (Karen Chang, Director of Finance)
Attachments: 1. Att 2 - Expenditure Detail Report as of 2-29-2024, 2. Att 3 Presentation, 3. Att 1 Revenue Detail Report as of 2-29-2024
Related files: 24-250
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Informational Report on Measure W FY 2023-24 financials update for Measure W. (Karen Chang, Director of Finance)

 

label

RECOMMENDATION

Recommendation

This report is informational and requires no formal action from the Committee.

 

Body

BACKGROUND/DISCUSSION

On November 3, 2015, South San Francisco residents approved a half-cent sales tax by an overwhelming majority.  The adoption of Measure W ensures that the City of South San Francisco will be able to maintain and enhance locally controlled City services that the community cares about and has come to expect - including neighborhood police patrols, 911 response times, crime and gang suppression programs, street maintenance and pothole repair, maintaining youth/teen educational/recreational programs, providing a police operations center that meets earthquake safety codes, and other essential services.

 

The voter-approved half-cent sales tax (Measure W) went into effect on April 1, 2016. Since that time, the sales tax proceeds have been accounted for separately from the City’s General Fund to track the commensurate revenues and expenditures. 

 

Major projects currently funded by Measure W are:

1.                     Community Civic Campus Program

a.                     Police Operations & 911 Dispatch Center (pf1707)

b.                     Library, Parks and Recreation and Community Theater/Council Chamber (pf2103)

2.                     Orange Memorial Park Project

a.                     Multi-Use Sports Fields

b.                     Aquatic Center

c.                     Park Playground

d.                     Park Bridges

3.                     Paving Program

Used to augment City efforts towards street maintenance and pothole repairs

 

 

 

 

A.                     MEASURE W FUND BALANCE THROUGH FEBRUARY 29, 2024

 

The following is a summary of Measure W revenues and expenditures since its inception through February 29, 2024:

 

 

Table 1: Measure W Fund Balance Summary

 

Fiscal Year Ended

Cumulative  Total as of  June 30, 2021

FY 21/22

FY 22/23

FY 23/24  (7/1/23 - 2/29/24)

Total as of February 29, 2024

Total Revenues

$59,270,645

$15,399,766

$15,618,697

$8,328,043

$98,617,151

 

 

 

 

 

 

Expenditures

 

 

 

 

 

Salaries & Benefits

267,867

279,785

287,295

109,704

944,651

Services & Supplies

275,622

 

 

 

275,622

Transfers Out to Capital Improvement Fund

 

 

 

 

-  

   Civic Campus

40,907,394

2,755,016

2,088,941

 

45,751,351

   Street Paving Program

6,711,687

159,012

44,071

-  

6,914,770

Debt Service

3,174,355

8,287,833

8,289,450

2,483,375

22,235,013

Total Expenditures

$51,336,925

$11,481,646

$10,709,757

$2,593,079

$76,121,407

 

 

 

 

 

 

Revenue Less Expenditures

$7,933,720

$3,918,120

$4,908,940

$5,734,964

$22,495,744

 

 

 

 

 

 

FUND BALANCE

$7,933,720

$11,851,840

$16,760,780

$22,495,744

$22,495,744

 

 

As shown above, the preliminary fund balance for Measure W as of June 30, 2023, was $16,760,780. The fund balance as of February 29, 2024, was $22,495,744.

 

 

B.                     FY 2023-24 REVENUES (July 1, 2023 - February 29, 2024)

 

The City has recorded approximately $8.3 million in Measure W sales tax revenues.  The amount represents receipts of sales tax collection up to December 2023.  There is usually a two-month lag in collection.

 

 

 

 

C.                     FY 2023-24 EXPENDITURES

 

The following is a summary of expenditures as of February 29, 2024:

 

Table 2: Expenditures

 

 

 

FY 23/24 Expenditure Budget

FY 23/24 YTD Actual as of 2/29/24

FY 23/24 Available Balance

Salaries and Benefits

$475,635

$109,704

$365,931

Civic Campus Construction (pf1707, pf2103)

12,111,127

0

12,111,127

Paving Program (st2104, st1903)

1,086,231

0

1,086,231

Debt Service

8,286,750

2,483,375

5,803,375

TOTAL Expenditures

$21,959,743

$2,593,079

$19,366,664

 

 

Ongoing Capital Project Funds appropriated in prior years by Council but unspent has been carried over as appropriated funds to be spent in FY 2023-24 or future years.

 

 

CONCLUSION

In FY 2023-24 (as of February 29, 2024), the City collected $8.3 million in Measure W sales tax revenues and expended $2.6 million.

 

Attachments:

 

1.                     Revenue Detail report - FY 2023-24 (As of February 29. 2024)

2.                     Expenditure Detail report - FY 2023-24 (As of February 29. 2024)

3.                     Power Point Presentations