Skip to main content
City of South San Francisco header
File #: 24-276    Name:
Type: Staff Report Status: Passed
File created: 3/11/2024 In control: City Council
On agenda: 7/24/2024 Final action: 7/24/2024
Title: Motion to accept the construction improvements of the HSIP Curb Ramp Improvements Project (tr2202) as complete in accordance with plans and specifications (Total Construction Cost $696,574.53). (Audriana Hossfeld, Senior Civil Engineer)
Attachments: 1. Attachment 1 - Vicinity Map, 2. Attachment 2 - Construction Photos

Title

Motion to accept the construction improvements of the HSIP Curb Ramp Improvements Project (tr2202) as complete in accordance with plans and specifications (Total Construction Cost $696,574.53). (Audriana Hossfeld, Senior Civil Engineer)

 

label

RECOMMENDATION

It is recommended that the City Council, by motion, accept the construction improvements of the Local Highway Safety Improvement Program Curb Ramp Improvements Project (tr2202) as complete in accordance with plans and specifications (total construction cost $696,574.53).

 

Body

BACKGROUND/DISCUSSION

On December 13, 2023, City Council awarded the Local Highway Safety Improvement Program (HSIP) Curb Ramp Improvements Project (tr2202) to RK Engineering of San Francisco, California.

 

The HSIP - Curb Ramp Replacement Project installed ADA-compliant curb ramps at five (5) unsignalized intersections:

                     Walnut Avenue and Lux Avenue

                     Walnut Avenue and Park Way

                     Olive Avenue and Pine Avenue

                     Olive Avenue and Aspen Avenue

                     Linden Avenue and 8th Lane

The work completed consisted of replacing existing concrete curb ramps or corners with ADA- compliant curb ramps, replacing sections of existing fractured or settled curb and gutter, replacing sections of existing fractured sidewalk where necessary, and reinstalling traffic striping at five (5) locations.

The Engineering Division inspected the work and found the project to be complete in accordance with the contract documents as of June 24, 2024. This staff report includes the project location map and construction photos as Attachments 1 and 2, respectively.

FISCAL IMPACT

This project (tr2202) is included in the City of South San Francisco’s fiscal year (FY) 2023-24 budget. There are sufficient funds in FY 2023-24 to cover the total construction contract costs.

The total construction cost incurred for the project is summarized as follows:

 

 

Projected

Actual

RK Engineering

$676,580.00

$673,943.35

Construction Contingency

$135,316.00

$22,631.18

Total Construction Budget

$811,896.00

$696,574.53

 

The total construction budget was approved by City Council on December 13, 2023. While the total construction cost could have been up to $811,896.00, the actual construction cost was $696,574.53, which represents a 14% savings.

 

The program includes the following funding sources:

 

Funding Source

Amount Used for tr2202 Construction

HSIP Grant

$249,000.00

Measure A

$200,000.00

Gas Tax

$175,000.00

San Mateo County Measure W

  $72,574.53

 

If there are remaining local funds available after the close of the project, they will be reallocated to other CIP projects.

 

RELATIONSHIP TO STRATEGIC PLAN

Approval of this action will contribute to the City’s Strategic Plan outcome of improved Quality of Life and Livability by both maintaining and improving accessible infrastructure.

CONCLUSION

Staff recommend acceptance of the project as complete. Upon acceptance, a Notice of Completion will be filed with the County of San Mateo Recorder’s Office. At the end of the thirty-day lien period, the retention funds will be released to the contractor after the City receives a one-year warranty bond.

Attachments:

1.                     Vicinity Map

2.                     Pre- and Post-Construction Photos